+86-13156192271      sales@yizhoulaser.net
Machine Installation and Test
You are here: Home » Blog Center » Machine Installation and Test

Machine Installation and Test

Views: 44     Author: Site Editor     Publish Time: 2021-05-31      Origin: Site

Machine Installation 



When you receive the machine, open the package, check the accessories in Packing  list with the machine. If quantity is not correct, please contact us. We will resend  again. 


1)Open the machine package 

2) Loosen the upper nuts of the feet with a wrench, and raise the feet to make the distance to the pallet greater than to the casters.

    移动1                移动2

Figure Loosing Casters and Feet   

3) Fork the machine from the pallet with a forklift, deliver to the destination, and  unscrew the feet.




Environmental requirements for installation


The installation site must be away from dust, dirt, humidity, and rain. The floor to be  placed must be flat and capable of carrying loads,

Preference is given to floors with sound-attenuating coverings to prevent the  transmission of mechanical vibrations.


The power connection, air compressor or air source at the installation site must be  consistent with the required specifications.


Power distribution specifications: 

1) Rated power 11KW,

2) The power cord is three-phase three-wire, 6-10 square millimeters. 

3) Leakage circuit breaker 200V-240V/60HZ-63A. Install to 3-8 meters  away from the machine.

4) Compressed air: pressure 0.4-0.7MPa, air pipe diameter 6MM;



Main accessories:


1) Electrical oscillating cutting head 

2)1 USB data cable, 1 network/web cable

3) 20 cutting knives

4One USB flash drive with machine control software and typesetting software,  manuals and videos 

5A set of tools



Electricity connection


1) Machine input power connection 

Open the back electrical box of machine, Connect 220V-240V/60HZ voltage three  phase as  


Figure  shows

连接电缆

Figure: Machine Electricity connection


Vacuum pump installation and electricity connection

1)vacuum pump installation

真空泵安装


Figure : Vacuum pump installation


2)Vacuum pump electricity connection to machine


真空


CONTACT US

If you have any questions, please feel free to contact us, we will give you a satisfactory answer.
  Yizhoulaser 
  0086-13156192271
  +86-531-83161816

BLOG CENTER

We design and manufacture high quality laser cutting systems.
Copyright  2019  Jinan YIZHOU Laser Technology CO.,Ltd.  |  Support by sdzhidian